Here is the latest update on the project:
- PCB Production: A total of 330 PCBs have completed initial production. Sample boards have been tested, and all test results meet the design requirements.
- Enclosure: The enclosure is currently under fabrication and progressing as planned.
- Cables: Cable samples are being manufactured.
- Automated Testing: We are developing the hardware and software for automated testing, which will be used to perform full functional testing of the ESP32JTAG hardware to ensure each unit is properly validated before shipment.
- Delivery Schedule Adjustment: Based on the remaining workload, meeting the original delivery target of February 15 will be challenging. While we have been working hard to keep the schedule, additional time is required, primarily for cable manufacturing and test solution development and validation.
As a result, we are updating the expected delivery date to March 31.
Thank you very much for your continued support and understanding. We will continue to provide updates and share further progress as it becomes available.