Project update 7 of 19
The Librem 13 is progressing forward nicely, it has a possibility of arriving at the earlier window, but we’ll keep the dates as is for now:
Dates:
August 15th – “green light” fabrication
August 20th – Todd on-site @ fabrication in Shenzhen
week 1 fabrication
week 2 fabrication
week 3 fabrication
week 4 fabrication
September [15th-20th] – Receive hardware for assembly
September [24th-28th] – Ship first orders
Known Issues:
Trackpad Driver
Unlocking the ME
Coreboot BIOS
Hardware Kill Switches
Bluetooth (via daughter card)
Thank you!
Todd Weaver & Purism Team todd@puri.sm