Weekly Update on Librem rev2 Production

We had two small motherboard fabrication issues with the Librem 15 rev2 (second) prototype Monday of this week, it was sent back to fabrication to resolve those issues Wednesday of this week, and we are expected to receive an updated version (our third prototype) in South San Francisco before Thursday, August 13th (being sent out priority Monday August 10th).

While we were hoping to approve the last prototype, we were not lucky in that hope, but the changes to the motherboard design were minor enough we got a quick turn around from fabrication.

To keep a running update on dates:

July 28th – Receive second prototype

August 3rd – Reject second prototype

>August 4th – Approve prototype

August 10th – Ship second prototype

August 13th – Receive third prototype (test)

August 17th – “green light” fabrication

August 20th – Todd on-site @ fabrication in Shenzhen

[3-4 weeks fabrication]

September [15th-20th] – Receive hardware for assembly

September [24th-28th] – Ship first orders of Librem 15 rev2

I will make an effort, as we approach this exciting milestone, to post updates on a weekly or more frequent basis.

Thank you!

Todd Weaver & Purism Team todd@puri.sm

$599,893 raised

of $250,000 goal

Funded! Order Now

Jan 31 2015

funded on

239%

funded

731

pledges

Product Choices

$5

Support Us!


$1,600

Librem Laptop Rev2


$50

Power Adapter

Credits

Purism

We build high-quality hardware that respects your essential freedoms.


Todd Weaver

Subscribe to receive the Crowd Supply weekly newsletter, highlighting the latest creators and projects: